LIST OF EMERGENCY PURCHASE AFFIDAVITS

                                              FILED WITH THE OFFICE OF THE AUDITOR

                                                      October 1, 2008 through December 31, 2008

  1       AUDITOR GENERAL -  OFFICE OF THE                           

                                                                                                                                   Filed:       10/2/2008

  To properly conduct the financial audit and compliance examination of Northern Illinois Research

  Foundation and related subsidiary for the one year ended June 30, 2008, the examination to begin as

  soon as possible.  Following internal discussions, it was determined we did not have sufficient internal

  staff resources to conduct this engagement.  Insufficient time exists to conduct the usual request for

  proposals competitive selection process prior to October 6, 2008.  A fair and reasonable price was

  negotiated with Clifton Gunderson LLP which has experience with the Auditor General's program and

  has sufficient staff and expertise to perform this audit and begin work within the necessary timeframe to

  avoid serious disruption in OAG audit services.

   Signed By: Bruce Bullard, Director

      Vendor:  Clifton Gunderson LLP                                                           Notary Date:           10/2/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $20,300.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

  2       AUDITOR GENERAL -  OFFICE OF THE                           

                                                                                                                                   Filed:       10/2/2008

  To properly conduct the compliance examination of Lawrence Correctional Center for the period ended

  June 30, 2008, the examination needs to begin as soon as possible.  The Office of the Auditor General

  issued a Request for Proposal to competitively procure the services, however, no responses were

  received.  Following internal discussions, it was determined we did not have sufficient internal staff

  resources to conduct this engagement.  A fair and reasonable price was negotiated with J.W. Boyle &

  Company which has experience with the Auditor General's program and has sufficient staff and expertise

  to perform this audit and begin work within the necessary timeframe to avoid serious disruption in

   Signed By: Bruce Bullard, Director

      Vendor:  J.W. Boyle & Company                                                          Notary Date:           10/2/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $44,763.28                                                  9                2

     Federal Cost                    $0.00                      $0.00

 


  3       SECRETARY OF STATE                                         

                                                                                                                                   Filed:      10/30/2008

  The roofing system on the Auditorium of the Michael J. Howlett Building has outlived its useful

  lifespan and can no longer be maintained through regular maintenance.  This will require the

  replacement of the Auditorium roofing system.  This emergency condition was discovered after the fall

  of water damaged plaster ceiling and wall material in various locations in the auditorium space.  To

  date we have identified approximately 3 areas, one on the East, one on the West, and one on the

  Southwest of the roof where water infiltration has occurred.  Due to the possiblity of employee health

  and safety being at risk because of the risk associated with this roof in its current condition, we feel it is

  necesssary to declare this an emergency.

   Signed By: Donna Fitts, Director

      Vendor:  Unknown                                                                               Notary Date:         10/29/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $167,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  4       SECRETARY OF STATE                                         

                                                                                                                                   Filed:      12/22/2008

  The emergency is required for the purchase of stoker coal, this coal is utilized at the State of Illinois

  Power Plant for steam heating purposes of several major state owned buildings in Springfield including

  the State Capitol Complex.  The purchase became an emergency due to the previous contract vendor

  terminating the contract due to major cost increases for the production of stoker coal at their facility. 

  The emergency purchase will allow the Secretary of State time to complete a formal bid process for

  stoker coal as required by State Statute that meets the minimum specifications required for plant

   Signed By: Donna Fitts, Director

      Vendor:  Capitol Sales LLC                                                                  Notary Date:         11/13/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $65,100.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  5       AGRICULTURE -  GENERAL OFFICE                              

                                                                                                                                   Filed:      12/30/2008

  An area of approximately 60' x 100' of the standing seam roof on the grandstand was tore loose from the

   deck during a storm.  Majority of the roof landed on the grandstand stage, which has also, been

  damaged.  There could be further damage if the section blows off during another storm or heavy winds

  and falls into the seating.

   Signed By: Thomas Jennings, Executive Director

      Vendor:  Unknown                                                                               Notary Date:         12/30/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $160,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  6       CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:       12/3/2008

  The Department of Central Management Services is giving notice of an emergency contract with SEPS,

  Inc. for Uninterruptible Power Supply (UPS) equipment, maintenance and engineering support.

   Signed By: Gwyn Gurgens, Acting SPO

      Vendor:  SEPS                                                                                     Notary Date:           12/2/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $51,200.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

  7       CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:      11/20/2008

  The State has a Financing Matrix Master Contract with the Vendor that provides a cost-effective and

  administratively efficient method of providing financing for State personal property acquisitions.  Due to

   the current credit crisis facing the United States, the Vendor has claimed force majeure.  The State

  disputes this claim.  Through an emergency contract amendment, the State and the Vendor will revise

  the contract pricing to continue to allow the State to access necessary financing for statewide

  procurements at a reasonable cost and effectuate a settlement of the disputed contract claim by the

   Signed By: Lynn Carter, Deputy General Counsel

      Vendor:  First Southwest Leasing Co.                                                    Notary Date:         11/14/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $60,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  8       CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:       12/8/2008

  This emergency procurement is necessary to extend this contract for a period of 12 months (12-15-08 -

  12-14-09) to allow for the solicitation, award and implementation of any replacement contract(s) via a

  forthcoming solicitation.  CMS is, via an Emergency Procurement, extending the existing

  Telecommunications Network Services contract which covers 95% of all the telecommunications

  circuits in the State.  If this agreement were to lapse, the State may be subject to increased cost under

  tariff rates, thus adversely effecting all State agency business.

   Signed By: Gwyn Gurgens, Acting SPO

      Vendor:  AT&T Global Services                                                           Notary Date:           12/5/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:         $35,592,161.49                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  9       CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:      12/15/2008

  The emergency procurement of cellular services for cellular services in Region 7, for the 9 month period

  of January 1, 2009 - September 30, 2009 is necessary due to the fact that the solicitation for a new

  Statewide Cellular Services contract is currently in process.

   Signed By: Gwyn Gurgens, Acting SPO

      Vendor:  AT&T                                                                                   Notary Date:         12/12/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $134,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  10     CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:      12/15/2008

  The emergency procurement of cellular services for cellular services in Regions 1-4 & 6 for the 9 month

  period of January 1, 2009 - September 30, 2009 is necessary due to the fact that the solicitation for a

  new Statewide Cellular Services contract is currently in process.

   Signed By: Gwyn Gurgens, Acting SPO

      Vendor:  Verizon Wireless                                                                    Notary Date:         12/12/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:           $6,000,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  11     CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:      12/15/2008

  The emergency procurement of cellular services for Sprint/Nextel Push-To-Talk feature for the 9 month

  period of January 1, 2009 - September 30, 2009 is necessary due to the fact that the solicitation for a

  new Statewide Cellular Services contract is currently in process.

   Signed By: Gwyn Gurgens, Acting SPO

      Vendor:  Sprint/Nextel                                                                          Notary Date:         12/12/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $915,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

  12     CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:      12/15/2008

  The emergency procurement of cellular services for cellular services in Region 5 for the 9 month period

  of January 1, 2009 through September 30, 2009 is necessary due to the fact that the solicitation for a

  new Statewide Cellular Services contract is currently in process.

   Signed By: Gwyn Gurgens, Acting SPO

      Vendor:  Illinois Valley Cellular                                                             Notary Date:         12/12/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $30,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

  13     NATURAL RESOURCES, DEPARTMENT OF                         

                                                                                                                                   Filed:       10/2/2008

  A sag type subsidence event formed on July 22, 2008 causing damage to five duplexes and 2

  quadplexes that are part of a senior citizen retirement village located in Springfield.  Given the severity

  of the problem, it was deemed necessary to forego normal program procedures which typically include

  the preparation of formal specifications and bid documents until after the fact in order to start work in a

  more timely fashion.  The initital contract executed was under the threshold of $39,000.  Movement

  continues, therefore additional scope being added.  Change Order #1 takes the procurement at the

  present at $49,446.24.

   Signed By: Norm Dixon, State Purchasing Officer

      Vendor:  SUNCON, Inc.                                                                      Notary Date:           10/1/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $49,446.24                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  14     NATURAL RESOURCES, DEPARTMENT OF                         

                                                                                                                                   Filed:       12/3/2008

  On October 20, 2008, the Department's long reach excavator became submerged in approximately 22 ft.

  of water when the White's Levee on which it was crossing gave way.  The location is near Cuba Island

  at the Sanganois State Conservation Area in Mason County, Illinois.  Notification was made to all

  emergency contacts including  the Illinois Environmental Protection Agency, the Illinois Emergency

  Management Agency and the National Response Center.  The IEMA incident no. is 20081558 and the

  NRC incident no. is 887704.  Contract was made with Enviro Vac of Jacksonville, Illinois, an

  emergency response contractor, to secure oil absorbing booms which were installed around the

  submerged equipment to contain any fuel/oil leakage that may have occurred, as suggested by IEPA,

  and to secure services for environmental cleanup and disposal efforts.  A local contractor with various

  heavy equipment was brought on-site to retrieve the excavator from the water.

   Signed By: Norm Dixon, SPO

      Vendor:  Various                                                                                  Notary Date:           12/2/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $56,196.83                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  15     CORRECTIONS - GENERAL OFFICE                               

                                                                                                                                   Filed:      10/31/2008

  Upgrading exiting Housing Unit yard area for use by Level II Segregation Inmates by constructing

  necessary security fencing and recreational pods to provide required recreational activity on inmates in a

  safe and secure manner.  Construction of security fencing and recreational pods must be completed and

  operational by December 1, 2008.

   Signed By: Lee Ryker, Warden

      Vendor:  Anthony Supply Company, Inc.                                                Notary Date:         10/17/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $80,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  16     CORRECTIONS - GENERAL OFFICE                               

                                                                                                                                   Filed:      10/31/2008

  The touchscreen security control system, digital recording system, GUI system that is used to operate

  all cell doors, lighting, exterior doors, intercoms, cameras is outdated.  Technical support is limited or

  nonexistent due to the fact that the operating system runs off of Windows NT which is unstable and

  outdated.  The digital recording system is inoperable since all of the hard drives need replaced. 

  Additional cameras are needed to monitor areas where there is currently no camera equipment such as

  the maximum security classrooms, library, and dietary which could put staff and inmate safety in

   Signed By: Frank Shaw, Warden

      Vendor:  Easter Owens Integrated System                                             Notary Date:         10/17/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $65,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  17     CORRECTIONS - GENERAL OFFICE                               

                                                                                                                                   Filed:      10/31/2008

  57 segregation pods are needed for highly aggressive segregation status, level one inmates and

  psychiatric or mentally ill offenders.  Recreation pods are necessary to accommodate required statutory

  recreation time for confined offenders.  Labor is also needed to unload, fabricate, erect, install and secure

  57 exterior recreation pods.

   Signed By: Frank Shaw, Warden

      Vendor:  Various                                                                                  Notary Date:         10/22/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $222,271.50                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  18     CORRECTIONS - GENERAL OFFICE                               

                                                                                                                                   Filed:       11/7/2008

  Snow dams up on buildings creating a hazard to staff, inmates, and State property.  The snow and/or

  ice when melting has the ability to avalanche and has avalanched onto persons or property.  The

  condition is a threat to staff, inmates and property.  A snow and ice detention system is needed for the

  entire length of the Programs building, Support building and above the staff and inmate entries in front

  of and behind Housing Units 1, 2, 3, 4.

   Signed By: Frank Shaw, Warden

      Vendor:  CARROM Construction                                                          Notary Date:         10/24/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $57,498.75                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  19     CORRECTIONS - GENERAL OFFICE                               

                                                                                                                                   Filed:      12/18/2008

  On November 24, 2007 the ceiling of C wing located in the minimum security unit completely

  collapsed onto inmate bunks and property.  The entire ceiling is completely destroyed and resting onto

  the resident bunks.  The ceiling must be replaced and the other remaining cell wing ceilings need to be

  inspected and defects repaired before residents can return to their respective wings.  The building

  remains vacant until a complete inspection has taken place.

   Signed By: Frank Shaw, Warden

      Vendor:  Unknown                                                                               Notary Date:         11/24/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $75,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  20     CORRECTIONS - GENERAL OFFICE                               

                                                                                                                                   Filed:      12/18/2008

  To establish an emergency purchase for vegan burger mix in order to fulfill ICI's commitment to current

   and future orders with the Department of Corrections throughout the State of Illinois.  The current

  vendor could not provide the vegan burger mix at the contracted price due to the required changes in the

   formulation of the vegan burger mix.  CMS has indicated the contract will have to be rebid and since

  this has traditionally taken a substantial amount of time ICI needs to be able to purchase now.

   Signed By: Sal Raymond, Asst. CEO

      Vendor:  Newly Weds Foods                                                                Notary Date:           12/9/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $39,400.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  21     CORRECTIONS - GENERAL OFFICE                               

                                                                                                                                   Filed:      12/24/2008

  Return hot water heater line is leaking in the Vocational building.  The necessary pipe buried in the

  ground that leads to R5 Cell House feeds off of the line leaking.  The pipe is underground and we have

  no way of knowing where the leak is coming from.  We have it contained to the outer emergency jacket.

    Have had conversations with the company who installed the original line and conversation has led us

  to believe that the line could burst at any moment.  Need to dig up line and replace it so that further

  damage is not caused by this leakage.  If the pipe bursts or gets any worse, we will lose heat the R5 cell

   house units.  We been informed that if the leakage is not corrected that it could damage or cause the

  boiler to explode.

   Signed By: Greg Schwartz, Acting Warden

      Vendor:  S.I. Piping                                                                              Notary Date:         12/18/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $100,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  22     HUMAN SERVICES, DEPARTMENT OF                               

                                                                                                                                   Filed:      10/30/2008

  Deficiencies in original roof design have resulted in the need for not only multiple re-shingling efforts by

   roof contractors as well as facility carpenters over the years, but also roof re-design and repair of all "c"

  and "d" buildings and "a" (administration) building (ballasted areas over Medical Department spaces,

  versus shingling).  CDB Project 321-190-045 PH-IV is in progress and is in the fourth phase of this

  facility-wide roof repair project that have been completed since the roof repair was first begun.

   Signed By: Curtis Thompson, State Purchasing Officer

      Vendor:  Bennett & Brosseau Roofing                                                   Notary Date:         10/29/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00             $666,100.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  23     HUMAN SERVICES, DEPARTMENT OF                              

                                                                                                                                   Filed:      12/16/2008

  ISD started the repairs to our MTW line between one pit and the ISD High School and gymnasium. 

  We were using the  services of our contractor, Doyle Plumbing, that we have an existing contract with

  to do the repairs under that contract.  We tested the MTW lines yesterday, 11-25-08 at 6:00 p.m. to see

   if the repairs were corrected.  After the test we still have a link between the repaired work and the pit. 

  To complete the repairs it will be above the small purchase threshold and the contract amount with our

  vendor.  It is estimated to complete the work is between $100,000 - $135,000 so we need to declare an

  emergency purchase to complete the work.  If we do not make these repairs we will not have heat in our

   high school building or gym.  Currently, we are using small make up boilers to heat the school, which

   can not handle the cold weather conditions.

   Signed By: Curtis Thompson, SPO

      Vendor:  Doyle Plumbing and Heating                                                   Notary Date:         12/11/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $135,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  24     HEALTHCARE AND FAMILY SERVICES, DEPT OF

                                                                                                                                   Filed:       10/8/2008

  In order to meet the Comptroller's deadline of October 10, 2008 for distribution with medical cards, an

  emergency purchase was required to complete the printing of an informational newsletter providing

  critical information on healthcare, preventive care, Illinois Health Connect, tips for staying healthy, and

  resource and contact information for all healthcare programs offered by the Department.  In order to

  maximize competition an informal bid was conducted by contracting approximately eight printing

  vendors.  The Department selected the lowest responsive vendor.

   Signed By: Thomas Sestak, State Purchasing Officer

      Vendor:  Phillips  Brothers Printing                                                        Notary Date:           10/6/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $41,627.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  25     REVENUE, DEPARTMENT OF

                                                                                                                                   Filed:       12/4/2008

  The Illinois Lottery's primary audit firm for evening Lottery drawings terminated its contract with the

  Lottery effective 12-1-08.  While an invitation for bid was issued as soon as possible after notice of

  termination was received, the process could not be completed, a contract awarded and executed, and a

  new firm trained prior to 12-1-08.  Consequently, it was necessary to retain an audit firm with drawing

  experience on an emergency basis beginning 12-1-08 in order to maintain the integrity of the Lottery's

  drawings.  Price quotes were obtained from the Lottery's two mid-day drawing audit firms and the

  emergency purchase awarded to the firm providing the low quote.

   Signed By: Norma Sutton, SPO

      Vendor:  Hill Taylor LLC                                                                      Notary Date:           12/3/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $20,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  26     TRANSPORTATION, DEPARTMENT OF                              

                                                                                                                                   Filed:      10/17/2008

  On July 21, 2008 the Department's bridge inspectors discovered stress fractures in the deck beams of the

   I-80 bridge, structure number 0810011 carrying Interstate 80 over the Mississippi River.  Due to the

  seriousness of the situation, the need to protect the infrastructure and provide safety to the motoring

  public, Department forces immediately placed traffic control to temporarily close the outside lanes until

  a certified traffic control company could install permanent lane closures.

   Signed By: George Ryan, Regional Engineer

      Vendor:  SELCO, Inc.                                                                          Notary Date:           10/6/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $14,410.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

 

  27     TRANSPORTATION, DEPARTMENT OF                              

                                                                                                                                   Filed:      10/30/2008

  Rising and receding water elevations on the Mississippi River during and after the June flood of 2008

  damaged the existing rip rap armament on the embankment fore slope along the riverside of IL Route

  100 from US Route 67 in Alton, IL to Vine Street in Grafton, IL.  Due to the magnitude of the damage,

   field reviews and engineering assessments were conducted by the Department's engineers and Federal

  Highway Administration representatives and it was determined that corrective action must be completed

   before the Spring 2009 rains.

   Signed By: Mary Lamie, Deputy Director

      Vendor:  Baxmeyer Construction, Inc.                                                   Notary Date:           10/7/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:           $6,200,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  28     TRANSPORTATION, DEPARTMENT OF                              

                                                                                                                                   Filed:       10/7/2008

  Rising water elevations on the Mississippi River during the flood of 2008 necessitate a temporary grade

   raise of IL Route 100 to maintain services.  Upon receding of the flood waters and removal of the

  temporary grade raise, damages to surface of IL 100 and adjacent bike trail and siltation/debris clogging

  the storm drainage system were observed.  Determination of funding reimbursement and subsequent on-

  site field meeting with FHWA resulted in the timing of this emergency affidavit submittal for

  signature/filing.  The proposed work will consist of milling and resurfacing of IL Route 100 and

  adjacent bike trail and the cleaning of the storm drainage system from State Street to the pavement 

  joint west of Williams Street in Alton, IL.

   Signed By: Mary Lamie, Deputy Director

      Vendor:  C.E. Mahoney Company                                                         Notary Date:           9/19/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $175,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  29     TRANSPORTATION, DEPARTMENT OF                              

                                                                                                                                   Filed:       10/7/2008

  Rising and receding water elevations on the Mississippi River during the June flood of 2008 has

  deposited silt in the inlets and storm drainage system along Kaskaskia Street/IL Route 3 truck by-pass

  around Chester, IL in Randolph County.  In additional to the siltation, tractor trailers driving through

  the floodwaters and over the concrete gutter caused damges to the gutter, inlets, and grates. 

  Determination of funding reimbursement and subsequent on-site field meeting with FHWA resulted in

  the timing of this emergency affidavit submittal for signature/filing.  The proposed work will consist of

  silt removal from the drainage system and removal/replacement of the damaged gutter, inlets, and

   Signed By: Mary Lamie, Deputy Director

      Vendor:  Carl Bannister Excavating Ser.                                                Notary Date:           9/19/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $165,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  30     TRANSPORTATION, DEPARTMENT OF                              

                                                                                                                                   Filed:      11/25/2008

  Emergency support the top of the concrete box culvert, SN 027-2501, IL 115 over drainage ditch, 4.1

  miles north of IL 116 in Ford County.  The Department's structural engineers have evaluated the box

  culvert and based on their evaluation the box culvert must be supported to maintain legal load carrying

  capacity.  The emergency declaration is being made to expedite repairs in order to prevent further

  damage to the structures and maintain normal traffic flow.

 

  A letter was received dated December 30, 2008 that this emergency is no longer necessary.

   Signed By: George Ryan, Regional Engineer

      Vendor:  Tobey's Construction and Cart.                                                Notary Date:         11/13/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $100,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  31     HISTORIC PRESERVATION AGENCY                               

                                                                                                                                   Filed:      12/15/2008

  Pullman SHS;  Factory Complex, Chicago, IL.  RES structure:  Restore the power and lighting

  circuitry at the RES building

   Signed By: Jan Grimes, Executive Director

      Vendor:  Unknown                                                                               Notary Date:         12/10/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $60,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  32     HISTORIC PRESERVATION AGENCY                               

                                                                                                                                   Filed:      12/15/2008

  Metamora Courthouse State Historic Site.  Chimney reconstruction, window frame and sash restoration,

   masonry restoration, roof repairs and mold-mildew abatement.

   Signed By: Jan Grimes, Executive Director

      Vendor:  Unknown                                                                               Notary Date:         12/10/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $345,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

 

  33     TOLL HIGHWAY AUTHORITY, ILLINOIS STATE              

                                                                                                                                   Filed:       11/5/2008

  The Tollway issued an RFP for cafeteria services and it selected and approved a vendor.  However, in

  finalizing the terms of the contract, the selected vendor made new and unreasonable contract demands

  effectively withdrawing as the Tollway's cafeteria vendor.  To continue to provide food and beverages to

   Tollway employees and customers, it is necessary to procure vending machine services on an

  emergency basis.

   Signed By: Tracey Smith, Chief of Administration

      Vendor:  ACE Coffee Bar, Inc.                                                             Notary Date:         10/27/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  34     TOLL HIGHWAY AUTHORITY, ILLINOIS STATE              

                                                                                                                                   Filed:       12/1/2008

  The exterior sealant needs to be replaced at the front entrance of the Central Administration building. 

  This will help prevent water infiltration.  The failed sealant allows water to enter into the rotunda and

  down column lines 9 and 10 and into the computer room.  This is the first process in a series of steps

  necessary to stop the water deterioration in our facility.  If this step is not taken, there will be extensive

  water damage to the structure of the building and in the interior, which can include computer

  equipment.  Also, this project needs to be finished prior to our roof replacement which is being

  competitively bid.  This work needs to be completed before other pending projects due to the weather

  conditions and because the other projects would fail to start without this project being completed first. 

  This will prevent the other projects from failing.

   Signed By: Tracey Smith, Chief of Administration

      Vendor:  Sauer & Sons Caulking                                                           Notary Date:         11/20/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $37,800.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  35     CHICAGO STATE UNIVERSITY                                   

                                                                                                                                   Filed:      10/29/2008

  CSU again seeks the services of Youngblood and Associates to conclude their executive search for a vice

   president for the university office of financial and administrative affairs.  CSU had a change in

  administration and the Board of Trustees of the University recommended that all administrative hiring

  would be made by the new interim president.  The interim president, addressing both the

  administrative and financial needs of the University, appointed an internal administrator from the ranks

  of the University to serve as interim vice president for financial and administrative affairs until a

  qualified candidate can be hired.  The interim appointment has become taxing upon the total

  administrative resources of the University and therefore, in an effort to prevent serious disruption of

  University services, it became necessary for the University to again engage the services of Youngblood

  and Associates to complete the executive search for a qualified candidate to fulfill this critical position.

   Signed By: Dr. Dean Justmann, Interim VP

      Vendor:  Youngbood Executive Search                                                  Notary Date:         10/27/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $29,500.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  36     GOVERNORS STATE UNIVERSITY                                 

                                                                                                                                   Filed:      10/30/2008

  The driveway and parking area leading to the north door of the OTS building was in need of repair and

  expansion.  Due to construction, additional parking is required.

   Signed By: Tracy Sullivan, SPO Designee

      Vendor:  Sanchez Paving                                                                      Notary Date:         10/29/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $41,006.25                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  37     GOVERNORS STATE UNIVERSITY                                 

                                                                                                                                   Filed:      12/22/2008

  Immediate repair to the hot and cold coils of an air handler for the HVAC system is required to control

  temperature within the zone assigned within the facility.

   Signed By: Tracy Sullivan, SPO Designee

      Vendor:  ECI Mechanical                                                                     Notary Date:         12/19/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $36,344.99                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  38     ILLINOIS STATE UNIVERSITY                                  

                                                                                                                                   Filed:       11/7/2008

  Shower bases in Watterson Towers Residence Hall are leaking and require immediate repairs due to the

  potential for ceiling collapse in rooms below the showers, the possible growth of mold and mildew in

  the ceilings, adjoining walls and flooring.  The health and safety of the student residents in this

  structure is of major concern and the potential for further damage and loss of services warrants an

  expedited repair of the facility.

   Signed By: Judy Johnson, Director of Purchases

      Vendor:  Transolid, Inc.                                                                        Notary Date:           11/6/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $83,999.50                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  39     NORTHERN ILLINOIS UNIVERSITY                               

                                                                                                                                   Filed:       10/6/2008

  This year the membership and bowl participation fees increased, resulting in delayed internal approvals.

   Once approvals were received there was insufficient time to publish notice on the bulletin.  Late

  payments would have jeopardized the university' standing in the athletic conference.

   Signed By: Eddie Williams, Exec. VP

      Vendor:  Mid-American Conference                                                      Notary Date:           10/2/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00             $230,000.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  40     NORTHERN ILLINOIS UNIVERSITY                               

                                                                                                                                   Filed:       11/7/2008

  This purchase is needed to secure specialized consulting support related to a serious issue associated

  with the university's People Soft System which is causing student accounts to be improperly billed

  and/or refunded.  Specialized services are needed to address system setup and to implement the

  corrective action needed in an environment requiring a detailed understanding of student financial

  business process, federal, state and other agency payment restrictions of student charges, student tuition

  and fee waivers and an understanding of the complex data structures and system processes associated

  with payment and charge priorities, payment equations and internal tuition calculation processes. 

  Corrective action is needed before the next billing cycle and before tuition can be recalculated for the

  spring semester.  Inability to or delay in securing these services will have a direct negative impact on

  university cash flow and the ability to register students for the spring semester and to assess accurate

  student charges.

   Signed By: Eddie Williams, Exec. VP

      Vendor:  Oracle USA, Inc.                                                                   Notary Date:         10/31/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $56,448.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  41     NORTHERN ILLINOIS UNIVERSITY                               

                                                                                                                                   Filed:      12/17/2008

  The services of Air Planning LLC were engaged for charter service to transport members of the

  University to the Independence Bowl in Shreveport, Louisiana on December 23 and 29, 2008.  There

  was insufficient time to bid this purchase from the time the University was invited to participate in the

   Signed By: Eddie Williams, Exec. VP

      Vendor:  Air Planning LLC                                                                   Notary Date:         12/15/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $130,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  42     NORTHERN ILLINOIS UNIVERSITY                               

                                                                                                                                   Filed:      12/22/2008

  The services of Clarion Hotel were engaged for lodging and meals for the University's football team from

  December 23, 2008 through December 29, 2008 while the team plays in the Independence Bowl in

  Shreveport, Louisiana.  There was insufficient time to bid this purchase from the time the University

  was invited to participate in the bowl game.

   Signed By: Eddie Williams, Exec. VP

      Vendor:  Clarion Hotel Shreveport                                                         Notary Date:         12/17/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $150,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  43     UNIVERSITY OF ILLINOIS                                     

                                                                                                                                   Filed:      10/10/2008

  The excavation and repair of the underground fire pump standpipe experienced multiple ruptures during

  a fire pump test in the Behavioral Sciences Building located at 1007 W. Harrison Street.  The building

  is fully occupied by faculty and students.  The fire sprinkler system had to be shutdown in order to

  excavate and repair the damaged pipe.  The emergency repair service is required to ensure life safety

  concerns to the occupants in the building.

   Signed By: Heather Haberaecker, Exec. Asst. VP

      Vendor:  J.S.R. Enterprises                                                                   Notary Date:           10/6/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $65,600.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  44     UNIVERSITY OF ILLINOIS                                     

                                                                                                                                   Filed:      11/17/2008

  This emergency purchase is required to provide hearing ability to patients following tumor removal for

  Neurofibromatosis Type 2 (NF2).  NFS patients lose the ability to hear following the tumor removal

  procedure. The University has 2 patients with progressing tumors which require surgery and will need

  this device to save their hearing ability.  Delaying this surgery leaves the patients at risk for significant

  tumor progression.  In addition, this is the only device approved by the FDA for use at the brainstem

  following NF2 removal to restore hearing.  One additional implant device is being purchased in order to

   have a backup system available during the surgical procedure.

   Signed By: Heather Haberaecker, Exec. Asst. VP

      Vendor:  Cochlear Americas Corp.                                                        Notary Date:         11/12/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $78,300.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  45     UNIVERSITY OF ILLINOIS                                     

                                                                                                                                   Filed:      11/17/2008

  This emergency purchase is required due to the fire at the College of Pharmacy Research Building. 

  These Cisco switches will be used to replace switches that were damaged during the fire on January 19,

  2008.  These switches provide the core connectivity of all computers within the College of Pharmacy to

   the campus network and commodity internet.

   Signed By: Heather Haberaecker, Exec. Asst. VP

      Vendor:  AT&T DataComm                                                                 Notary Date:         11/12/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00             $184,369.93                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  46     UNIVERSITY OF ILLINOIS                                     

                                                                                                                                   Filed:      11/21/2008

  This emergency expenditure is for a used SLA 250/50 stereolithography system.  The Micro and

  Nanotechnology Lab was recently awarded a $2.5 M grant by the U.S. Army Medical Research and

  Material Command to design and generate complex 3-D tissue with tunable microarchitecture. 

  Specifically, the department's task is to adapt stereolithography to create tissue consisting of living

  cells, biomaterials, and other biologically-relevant substances.  Because it is the only known piece of

  equipment available that can be used for this application, is it important to purchase it as soon as

  possible before it is sold to another customer.

   Signed By: Philip Abruzzi, SPO Designee

      Vendor:  Anza Incorporated                                                                  Notary Date:         11/19/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:                       $0.00              $60,000.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  47     SECRETARY OF STATE                                         

                                                                                                                                   Filed:       2/15/2008

  A letter was received dated October 23, 2008 reporting the actual cost of item #3 in our April 15, 2008

  report as $226,265.27.

   Signed By: Donna Fitts, Director

      Vendor:  Various                                                                                  Notary Date:           2/15/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $300,000.00             $226,265.27                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  48     CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:       5/21/2008

  A letter was received dated October 23, 2008 reporting the actual cost of item #11 in our July 15, 2008

  report as $224,500.

   Signed By: Gwyn Gurgens, Acting SPO

      Vendor:  CDB                                                                                      Notary Date:           5/21/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $275,000.00             $224,500.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  49     CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:         8/7/2008

  A letter was received dated November 6, 2008 reporting the actual cost of item #4 in our October 15,

  2008 report as $94,798.

   Signed By: Marcia Armstrong, Acting Deputy Director

      Vendor:  J T Packard & Associates                                                      Notary Date:             8/6/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $94,798.00              $94,798.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  50     CENTRAL MANAGEMENT SERVICES                                

                                                                                                                                   Filed:       5/30/2008

  A letter was received dated December 22, 2008 reporting the actual cost of item #12 in our July 15,

  2008 report as $329,001.74.

   Signed By: Gwyn Gurgens, Acting SPO

      Vendor:  SEPS, Inc.                                                                             Notary Date:           5/29/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $217,954.25             $329,001.74                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  51     CONSERVATION - NATURAL RESOURCES                           

                                                                                                                                   Filed:       5/23/2008

  A letter was received dated October 24, 2008 reporting the actual cost of item #17 in our July 15, 2008

  report as $89,679.38.

   Signed By: Norman Dixon, SPO

      Vendor:  Schomburg & Schomburg Const.                                             Notary Date:           5/22/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $59,969.00              $89,679.38                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  52     CORRECTIONS, CORRECTIONAL CENTER - DWIGHT       

                                                                                                                                   Filed:       7/24/2007

  A letter was received dated November 10, 2008 reporting the actual cost of item #11 in our October 15,

  2007 report as $7,763.

   Signed By: Mary Sigler, Warden

      Vendor:  Adler Roofing                                                                         Notary Date:           7/18/2007

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $50,000.00                $7,763.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

  53     CORRECTIONS - GENERAL OFFICE                               

                                                                                                                                   Filed:       1/30/2008

  A letter was received dated November 10, 2008 reporting the actual cost of item #21 in our April 15,

  2008 report as $6,655.65.

   Signed By: Mary Sigler, Warden

      Vendor:  Albrecht Well Service                                                             Notary Date:           1/16/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $35,000.00                $6,655.65                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  54     CORRECTIONS - GENERAL OFFICE                               

                                                                                                                                   Filed:       9/23/2008

  A letter was received dated November 10, 2008 reporting the actual cost of item #15 in our October 15,

  2008 report as $36,300.

   Signed By: Karen McKinney, Superintendent

      Vendor:  Unknown                                                                               Notary Date:             9/8/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $57,600.00              $36,300.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  55     STATE POLICE, DEPARTMENT OF                                

                                                                                                                                   Filed:       3/20/2008

  A letter was received dated November 19, 2008 reporting the actual cost of item #28 in our April 15,

  2008 report as $196,799.

   Signed By: Larry Trent, Director

      Vendor:  Unknown                                                                               Notary Date:           3/20/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $219,000.00             $196,799.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  56     TRANSPORTATION, DEPARTMENT OF                              

                                                                                                                                   Filed:       9/15/2008

  A letter was received dated November 3, 2008 reporting the actual cost of item #30 in our October 15,

  2008 report as $299,636.87.

   Signed By: Roger Driskell, Region 4 Engineer

      Vendor:  Unknown                                                                               Notary Date:           8/29/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $400,000.00             $299,636.87                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  57     TRANSPORTATION, DEPARTMENT OF                              

                                                                                                                                   Filed:       6/23/2008

  A letter was received dated December 5, 2008 reporting the actual cost of item #31 in our July 15, 2008

   report as $752,530.86.

   Signed By: Diane O'Keefe, Deputy Director

      Vendor:  Central Blocktop Company, Inc.                                              Notary Date:             6/5/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $900,000.00             $752,530.86                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  58     TRANSPORTATION, DEPARTMENT OF                              

                                                                                                                                   Filed:       8/14/2008

  A letter was received dated December 8, 2008 reporting the actual cost of item #23 in our October 15,

  2008 report as $343,205.15.

   Signed By: Roger Driskell, Regional 4 Engineer

      Vendor:  W.L. Miller                                                                            Notary Date:             8/6/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $375,000.00             $343,205.15                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

  59     TRANSPORTATION, DEPARTMENT OF                              

                                                                                                                                   Filed:         1/8/2008

  A letter was received dated December 5, 2008 reporting the actual cost of item #29 in our April 15,

  2008 report as $789,215.

   Signed By: George Ryan, Regional Engineer

      Vendor:  H.J. Eppel and Company, Inc.                                                 Notary Date:         12/21/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $800,000.00             $789,215.00                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  60     HISTORIC PRESERVATION AGENCY                               

                                                                                                                                   Filed:       7/24/2007

  A letter was received dated December 11, 2008 reporting the actual cost of item #39 in our October 15,

  2007 report as $95,686.01.

   Signed By: Robert Coomer, Director

      Vendor:  Unknown                                                                               Notary Date:           7/23/2007

                                      Estimate                   Actual                                                  FY             QT

     State Cost:             $120,000.00              $95,686.01                                                  9                2

     Federal Cost                    $0.00                      $0.00

 

 

  61     HISTORIC PRESERVATION AGENCY                               

                                                                                                                                   Filed:       1/14/2008

  A letter was received dated December 11, 2008 reporting that no action was taken as an emergency

  affidavit on item #35 in our April 15, 2008 report.  This item has been cancelled.

   Signed By: Jennifer Tirey, Acting Director

      Vendor:  Unknown                                                                               Notary Date:           1/11/2008

                                      Estimate                   Actual                                                  FY             QT

     State Cost:               $50,000.00                      $0.00                                                  9                2

     Federal Cost                    $0.00                      $0.00