REPORT DIGEST CAPITAL DEVELOPMENT BOARD FINANCIAL
AUDIT For the One Year Ended: June 30, 2008 And COMPLIANCE
EXAMINATION For the Two Years Ended: June 30, 2008 Summary of Findings: Total this audit 5 Total last audit 8 Repeated from last audit 3 Release Date: February 11, 2009
State of
Office of the Auditor General WILLIAM G. HOLLAND AUDITOR GENERAL
To obtain a copy of the
Report contact: Office of the Auditor
General Attn: Records Manager
(217) 782-6046 or TTY (217)
524-4646 This Report Digest and Full
Report are also available on the worldwide web at www.auditor.illinois.gov
|
SYNOPSIS¨ Adequate controls were not maintained over the collateralization of construction retention trust accounts. ¨ Requirements of the Art-in-Architecture Program were not met. {Expenditures and Activity Measures are summarized on the reverse page.} |
CAPITAL
DEVELOPMENT BOARD
FINANCIAL AUDIT
EXPENDITURE
STATISTICS |
FY 2008 |
FY 2007 |
FY 2006 |
· Total Expenditures (All Funds)*....... OPERATIONS TOTAL...................... % of Total Expenditures................ Personal Services........................... % of Operations Expenditures.. Average No. of Employees...... Other Payroll Costs (Retirement, Social Security, Group Insurance). % of Operations Expenditures.. Contractual Services...................... % of Operations Expenditures.. All Other Operations Items............. % of Operations Expenditures.. CONSTRUCTION TOTAL................ % of Total Expenditures................ · Cost of Property and Equipment...... · Cost of Construction in Progress...... |
$222,085,157
$13,308,781 6.0% $7,663,215 57.6% 130 $3,480,648 26.1% $553,209 4.2% $1,611,709 12.1%
$208,776,376
94.0%
$2,024,847
$18,045,024 |
$363,027,378
$12,352,575 3.4% $7,323,181 59.3% 126
$2,971,822 24.0% $467,019 3.8% $1,590,553 12.9%
$350,674,803 96.6%
$2,149,175
$44,117,432 |
$466,490,466
$10,959,319
2.3%
$6,582,567
60.1%
136
$2,607,630
23.8%
$354,121
3.2%
$1,415,001
12.9%
$455,531,147
97.7%
$2,309,051 $26,494,174 |
SELECTED ACTIVITY
MEASURES |
FY 2008 |
FY 2007 |
FY 2006 |
Number of Active Construction Projects.... Number of Design Contracts Processed...... Average Variation from Planned Schedule: Design Phase............................................ Construction Phase................................... Number of Change Orders......................... Percent of Change Orders to Contract Value |
296 87
40.98% 6.47% 1,516 5.57% |
426 139
11.4% -6.3% 1,998 7.6% |
443 39 34.8% 31% 1,808 6.87% |
* Appropriated and non-appropriated funds
EXECUTIVE DIRECTORS |
During Audit Period: James Riemer, Executive Director (5/13/08 through present) James Riemer, Acting Executive Director (4/16/08 through 5/12/08) Janet Grimes, Executive Director (7/1/06 through 4/15/08) Currently: James Riemer, Executive Director |
Local funds of $1.922
million were uninsured and uncollateralized
Projects lacked proof of installment insurance for artists
Projects did not have minutes from committee meetings
Public Arts Advisory Committee positions were vacant,
including the Chairman |
INTRODUCTION The
Capital Development Board serves as the non-road, construction management arm
of the FINDINGS, CONCLUSIONS AND RECOMMENDATIONS INADEQUATE INTERNAL CONTROL FOR UNINSURED AND UNCOLLATERALIZED
DEPOSITS The Board did not maintain adequate controls over the collateralization of locally held construction retention trust accounts. At June 30, 2008, the Board had a total bank balance of $5.82 million held in local funds as retainage on open construction projects, including $1.922 million which was uninsured and uncollateralized. The Board did not obtain additional collateral for some deposit amounts exceeding the Federal Deposit Insurance Corporation coverage. (Finding 1, pages 11-12) This finding was first reported in 2005. We recommended the Board continue to monitor account balances and act to ensure that bank accounts are collateralized adequately.
Board officials agreed with our finding. The Board responded that a new policy was implemented January 1, 2008 that new retention trust agreements will be allowed only if the bank complies with collateralization requirements. (For previous response, see digest footnote #1.) OTHER FINDINGS The remaining findings are reportedly being given attention by the Board. We will review the Board’s progress toward the implementation of our recommendations in our next compliance examination engagement. AUDITORS’ OPINIONOur auditors stated the financial statements of the Capital Development Board for the year ended June 30, 2008 are fairly presented in all material respects. ____________________________________ WILLIAM G. HOLLAND, Auditor General WGH:LKW SPECIAL ASSISTANT AUDITORS E.C. Ortiz & DIGEST FOOTNOTE #1 INADEQUATE INTERNAL CONTROL FOR
UNINSURED AND UNCOLLATERALIZED DEPOSITS-Previous Board Response 2007: We agree with the finding. CDB
sent agreement amendments requiring collateralization to 71 accounts. Responses
were returned by 24. Those not
responding with a signed agreement cited their inability to provide the
collateralization due to internal guidelines or a prohibitive cost. CDB will
begin a new policy that new retention trust agreements be allowed only if the
bank specifically responds to the collateralization requirement beginning
January 1, 2008. Those accounts
already in place will remain. We
understand that the potential for a repeat finding will exist until the old
accounts are all paid out. |