REPORT DIGEST Study STATES CONSTRUCTION CONTRACTING METHODS Released: April 2002
State of Illinois WILLIAM G. HOLLAND To obtain a copy
of the report contact: TDD: (217) 524-4646 This report is also available on the
worldwide web at: |
SYNOPSIS Senate Resolution Number 147 directed the Auditor General to study the effects of eliminating the five separate specifications for bidding on State construction contracts. The Procurement Code requires the Capital Development Board to use the "multiple prime" construction contracting method for projects costing at least $250,000. Capital Development Board. CDB provided several cost estimates for adding masonry as a separate (sixth) prime in a fiscal note and during this study see footnotes in Digest Exhibit 3.
|
|||||||||||||||||||||||||
Regarding
single prime versus multiple prime: States. In our mail survey, 26 of 32 states that responded primarily used the single prime method of construction. Design/build. In our survey, 26 of 32 states that responded used design/build (which has a combined contract for design and construction) for a small percentage of their projects. The fiscal impact on the State, contractors, and subcontractors by changing to single prime is not conclusive due to a wide range of differing information. Therefore, the General Assembly may wish to consider establishing a pilot program that authorizes CDB to use various construction contracting methods on a limited basis. |
CDB's March 2001 fiscal note estimated a cost of $45 million for adding masonry as a sixth prime contractor/ In February 2002, CDB provided us a revised cost estimate of $8.9 million over a 3-year project cycle, or $3 million per year.
CDB's 1997 report said multiple prime contracting was 5% less expensive. CDB's current position is that multiple prime is 10% more expensive.
The General Assembly may wish to establish a pilot program that authorized various construction contracting methods on a limited basis. |
REPORT CONCLUSIONS The Illinois Procurement Code requires the Capital Development Board to use multiple prime contracting for projects over $250,000 involving the construction or renovation of office buildings, prisons, warehouses, or other structures. The Procurement Code specifies the five prime contractors which are used if the work for two or more trades exceeds $32,400 (see inset).
We obtained input from State agencies, contractors, architecture/ engineering firms, professional trade associations, other states, and other governmental organizations. These entities had varying perspectives which may have been influenced by their economic interests. CAPITAL DEVELOPMENT BOARD. CDB said the single prime construction contracting method would be less expensive but it was up to the General Assembly to decide which method should be used by the State.
CONTRACTORS. General contractors indicated cost would remain the same or decrease under single prime while the remaining (or specialty) contractors indicated cost would remain the same or increase under single prime. STATES. In our survey, 26 of 32 responding states said they primarily used the single prime construction contracting method. DESIGN/BUILD. Design/build is a method which combines the contracts for architects and engineers (A/E) and construction into one contract. Over 80 percent (26 of 32) of the states responding to our survey used design/build for a small percentage of their projects, typically projects that need to be completed quickly. CDB and the University of Illinois would like the authority to use design/build for some projects. $250,000 THRESHOLD. The Procurement Code requires using multiple prime contracting for projects exceeding $250,000. The Capital Development Board, the Department of Corrections, the University of Illinois, and the A/E associations indicated that the $250,000 threshold requiring multiple prime contracting was low. The $250,000 threshold has not been adjusted for inflation since it was established in 1995. MATTER FOR GENERAL ASSEMBLY. The fiscal impact on the State, contractors, and subcontractors by changing to the single prime construction contracting method is not conclusive due to widely differing information. Therefore, the General Assembly may wish to consider establishing a pilot program that authorizes the Capital Development Board to use on a limited basis various construction contracting methods. (pages 1-4) BACKGROUND Senate Resolution Number 147 directed the Auditor General to study the effects of eliminating the five separate specifications for bidding on State construction contracts. In March 2001, the Capital Development Board (CDB) issued a fiscal note for Senate Bill 735 which said making masonry a separate (sixth) prime would cost the State an additional $45 million per year. The request for this study was a result of the fiscal note. During fiscal year 2001, CDB completed a total of 248 projects that had 458 contracts using the five trades listed in the Procurement Code (see Digest Exhibits 1 and 2). The expenditures for these 248 projects were $195,033,681: approximately 21 percent were single prime, while the remaining 79 percent were multiple prime. Most of the expenditures were for general contractors ($117,985,180). |
Digest Exhibit 1 |
|||||||
Prime (Trade) | Single Prime |
Multiple Prime |
Total |
||||
Contracts |
Expenditure |
Contracts |
Expenditure |
Contracts |
Expenditure |
% of $ |
|
General | 122 |
$29,670,581 |
86 |
$88,314,598 |
208 |
$117,985,180 |
60% |
Electrical | 13 |
$3,041,172 |
70 |
$21,001,572 |
83 |
$24,042,744 |
12% |
Heating | 13 |
$4,150,615 |
41 |
$17,013,455 |
54 |
$21,164,070 |
11% |
Plumbing | 11 |
$3,804,163 |
60 |
$14,904,846 |
71 |
$18,709,009 |
10% |
Ventilation | 2 |
$233,156 |
40 |
$12,899,522 |
42 |
$13,132,678 |
7% |
TOTAL |
161 |
$40,899,688 |
297 |
$154,133,994 |
$195,033,681 |
100% |
|
Note: Totals may not
add due to rounding. Source: CDB data analyzed by the Illinois Auditor Generals Office. |
33 of 248 projects totaled 67% of the expenditures. Each of these 33 projects were at least $1 millions. |
Out of the 134 projects that were greater than $250,000, there were 101 projects that were between $250,000 and $1 million; they totaled $48 million. The remaining 33 projects were at least $1 million each and totaled $131 million, or 67 percent of $195 million. Digest Exhibit 2 shows that 3 of the million dollar projects were single prime while the remaining 30 projects, totaling $127 million (65%), were multiple prime. CDB had difficulty providing all the data on projects closed during fiscal year 2001, including their change orders. CDB officials said the problem was in extracting specific data, including the fields we had requested, and they were in the process of upgrading their computer software. (pages 9-13) |
Digest Exhibit 2 |
||||||
Size | Single |
Expenditure |
Multiple |
Expenditure |
Total |
Expenditure |
Up to $250,000 | 104 |
$14,165,272 |
10 |
$1,417,558 |
114 |
$15,582,830 |
$250,000 to $999,999 | 54 |
$22,669,758 |
47 |
$25,713,718 |
101 |
$48,383,477 |
$1 million and more | 3 |
$4,064,658 |
30 |
$127,002,717 |
33 |
$131,067,375 |
TOTAL |
161 |
$40,899,688 |
87 |
$154,133,994 |
248 |
|
Note: Totals may not add due to rounding. | ||||||
Source: CDB data analyzed by the Illinois Auditor Generals Office. |
FISCAL NOTE During the 92nd General Assembly, Senate Bill 735 was introduced to amend the Illinois Procurement Code and add masonry to the list of separate specifications required for building construction projects in excess of $250,000. In March 2001, CDB issued a fiscal note for Senate Bill 735 which said that making masonry a sixth prime would increase the States construction cost by $45 million per year. CDB said the fiscal note was calculated in a matter of hours and was not correct because it was based on 10 percent of all construction projects, not just masonry projects (see Digest Exhibit 3). In the fall of 2001, CDB provided a revised cost estimate of $14.4 million based on projects that were in the system at the time, if masonry was added as a sixth prime (or $4.8 million per year). In February 2002, CDB provided an estimate based on appropriations for fiscal years 1999-2001 and excluded single prime contracts (21%). This revised estimate for making masonry a sixth prime was approximately $8.9 million (or $3 million per year). (pages 15-19) |
Digest Exhibit 3 |
||||
Date | Estimate |
Cost Basis |
Period Covered |
Cost/Year |
March 27, 2001 (Fiscal Note) | $45,000,000 |
Expenditures |
1 year |
$45.0 million |
August 24, 2001 | $14,436,480 |
Appropriations |
Not specified |
n/a |
October 25, 2001 | * $14,436,480 |
Appropriations |
3-year project cycle |
$4.8 million |
February 28, 2002 | ** $8,922,390 |
Appropriations |
** 3 years |
** $3.0 million |
*** $6,415,212 |
Expenditures |
3 years |
$2.1 million |
|
Note: The
Cost/Year column was added by the Office of the Auditor General to provide a consistent
time period for perspective. * CDB estimate based on projects that were in the system at the time. ** CDB estimate based on actual new appropriations for fiscal years 1999-2001. Excludes pass-through funds, projects that were single prime (21%), and the increased administration cost that was included in CDBs fiscal note. CDB said that ". . . construction does not occur neatly over a one year period, but rather varies anywhere from 1-6 years . . . ." *** CDB provided an estimate based on expenditures in response to our fieldwork summary but said the focus should be on the total funds appropriated for a project rather than the years over which expenditures are actually incurred. |
||||
Source: CDB data analyzed by the Illinois Auditor Generals Office. |
CDB provides a range of cost estimates for adding masonry as a sixth prime contractor.
Supporting documents were not available for CDB's cost estimate.
Under single prime, the State has only one contractor to hold responsible.
Under multiple prime, subcontractors are paid directly by the State so their payments are not held by general contractors.
Larger general contractors said single prime would have a positive impact on them. Medium and small contractors said single prime would have a negative impact on them. |
COST OF MAKING MASONRY A SIXTH PRIME CDBs Executive Director wrote to the Auditor General on August 24, 2001 that adding masonry as a sixth prime contractor would increase the cost of masonry by 10.3 percent due to 10 factors. CDB assigned each factor precise costs ranging from 0.1 percent to 2 percent. CDB added that single prime would save the State 10.3 percent for eliminating each of the four specialty trades for a total of $98.9 million. We learned the memos were based on CDBs experience and professional knowledge in addition to discussions with other states and contractors; therefore, supporting documents were not available with the exception of published reports and some information about other states. Because CDB also used these 10 factors to project $98.9 million in savings to the State under a single prime method, it was important to verify CDBs methodology. If there had been supporting documentation for the memo, we could have:
CDBs August 24, 2001 memo listed the advantages of single prime and multiple prime construction contracting methods. CDB later stated that the memo "was taken from over five written reports and information gathered from forty states":
PREVIOUS REVIEWS An internal evaluation conducted by CDB in 1997 concluded that the State saves five percent by using multiple prime contracting. CDB has now distanced itself from the report and CDB officials said the evaluation team looked at construction contracting methods from an administrative standpoint and were directed to work within the existing statutes.
We also reviewed reports regarding single versus multiple prime from New York City, North Carolina, Illinois Mechanical and Specialty Contractors Association (IMSCA), and others. These reports came to differing conclusions (see inset). A 1995 report for the national Electrical Contracting Foundation/Mechanical Contracting Foundation, which concluded that multiple prime was more than five percent less expensive than single prime, said that ". . . preferences seemed to be driven largely by the particular interest of the parties in question whether general contractors, specialty contractors or construction authorities." CDB did a test in 1993 and obtained both single and multiple prime bids for two University of Illinois projects in Chicago. Both projects received higher bids of at least 5½ percent for single prime.
CONTRACTORS AND A/Es In response to our mail survey questionnaire, the larger general contractors said single prime would have a positive or no impact on them, while the medium and small contractors said single prime would have a negative impact on them (see Digest Exhibit 4). The professional trade representatives of specialty contractors and architects/engineers said the following:
|
|
|
Digest Exhibit 4 |
||||
Effect on Cost if State Switched to Single Prime |
||||
Increase |
No Change |
Decrease |
||
1. Design Cost |
General | 7% |
68% |
25% |
Specialty | 23% |
69% |
8% |
|
Others | 11% |
78% |
11% |
|
Total Contractors |
14% |
71% |
14% |
|
A/Es | 4% |
39% |
57% |
|
2. Construction Cost |
General | 31% |
23% |
46% |
Specialty | 74% |
22% |
5% |
|
Others | 40% |
43% |
17% |
|
Total Contractors |
50% |
28% |
23% |
|
A/Es | 39% |
29% |
32% |
|
3. Change Order Cost |
General | 31% |
41% |
28% |
Specialty | 75% |
22% |
3% |
|
Others | 43% |
48% |
9% |
|
Total Contractors |
51% |
35% |
13% |
|
A/Es | 14% |
50% |
36% |
|
4. Litigation Cost |
General | 8% |
57% |
36% |
Specialty | 50% |
45% |
5% |
|
Others | 25% |
64% |
11% |
|
Total Contractors |
29% |
54% |
17% |
|
A/Es | 4% |
58% |
38% |
|
5. Coordinating Contractor Cost |
General | 32% |
27% |
41% |
Specialty | 69% |
23% |
8% |
|
Others | 50% |
43% |
7% |
|
Total Contractors |
51% |
30% |
19% |
|
A/Es | 36% |
46% |
18% |
|
Notes:
- "Others" refers to contractors who were not clearly general or specialty contractors. - May not total to 100% due to rounding. Source: Illinois Auditor Generals survey of contractors and A/Es (2001). |
26 of 32 states responding to our survey use single prime contracting.
CDB, Corrections, University of Illinois, and A/Es said the threshold requiring multiple prime contractors for projects over $250,000 is low.
CDB has used change orders to settle disputes between contractors. This could be expensive because change orders may have a 26 1/2% mark-up.
University of Illinois officials suggested combining the prime contractors for heating/cooling and ventilation into one prime contractor to eliminate gaps.
There were differing views on the various construction contracting methods. CDB favored single prime. |
SURVEY OF STATES In our survey, 26 of 32 states that responded said they primarily used single prime. Only five responding states, including Illinois, use multiple prime. One state (Florida) primarily uses the "construction manager at risk" method in which the contractor assumes the risk for completing the project for the projected cost. States wrote that single prime holds one contractor responsible, avoids gaps and overlaps between contracts, and simplifies management. They also noted that multiple prime improves payment to subcontractors and reduces bid shopping but is more difficult to coordinate and results in more administrative overhead. (pages 43-47) DESIGN/BUILD Over 80 percent of the states (26 of 32) who responded to our survey said they used design/build, however, only for a small percentage of their projects. Federal government agencies also use design/build for some projects. For example, the General Service Administration uses it for approximately 10 percent of its projects. Design/build is a construction method that combines design and construction into one contract. States often use design/build for uncomplicated projects or for projects that need to be completed quickly. The Capital Development Board and the University of Illinois would like the authority to use design/build for some projects. Currently, the Illinois Procurement Code does not specifically authorize design/build. (pages 49-53) THRESHOLD OF $250,000 The Capital Development Board, the Department of Corrections, the University of Illinois, and the A/E trade representatives indicated that the $250,000 threshold requiring multiple prime contracting was low. In fiscal year 2001, CDB completed 248 projects that had 458 contracts:
CDB noted that a reduction in administration could allow its project managers to devote more time to the larger, more complex projects. CDB officials noted that their project managers job is paper intensive as they spend considerable time reviewing forms and bills and attending meetings. They said that single prime would free up project managers time for more on-site monitoring. A higher threshold may also increase the opportunities for minority and female subcontractors. (pages 55-57) CHANGE ORDERS CDB officials said the agency has used change orders to avoid litigation and to settle disputes. Settling problems by using change orders also may not be the least expensive method for the State given the mark-up that must be paid. As shown in Digest Exhibit 5, change orders could have a 26½ percent mark-up. Change orders are not required to be competitively bid which may result in the State not getting the best price.
A mark-up is also permitted on deduct change orders to cancel work that had been bid. For example, a project had a deduct change order after the A/E developed a method to save the State $450,000, however, the agency had to pay the contractor 18 percent (or $81,000) for doing no work. CDB did not keep records of such change orders to show the total amount paid for resolving disputes. Making payments through change orders, especially without tracking (e.g., coding, summarizing, reporting, authorizing) has the potential to become problematic if project managers pay to resolve disputes without making upper management fully aware of the real reason for the change. Change orders up to $50,000 do not require the Directors review. (page 58) HEATING/COOLING AND VENTILATION University of Illinois officials said there are two related but separate primes that could be combined to save the State money. These two primes are heating/cooling and ventilation contractors. University officials said the primes were separate decades ago when the industry was using steam and it now makes sense to combine the two primes because they must interact together and may even be bid by the same company. University officials noted that frequently there is a "gap" between the ventilation and heating/cooling which would be eliminated if these prime contracts were bid as one package. North Carolina, Ohio, and New York, which are among the states that use multiple prime, combine heating/cooling and ventilation. (page 59) CONCLUSION According to CDBs fiscal note for Senate Bill 735 in March 2001, the State expends approximately $450 million per year on construction projects managed by the Capital Development Board. These projects are for many different State agencies, including the University of Illinois and the Illinois Department of Corrections which have many construction projects. During this study, we: obtained information from federal, State, and local organizations; surveyed other states, construction contractors, and architects and engineers; and met with the representatives of the professional trade associations for contractors and A/Es on CDBs Industry Advisory Committee. These entities had differing perspectives regarding the various construction contracting methods. Even when the overall percentage for a group favored a certain method, the responses were not homogeneous and there was variance in the group. In order to provide an overall perspective, they may be broadly summarized as follows:
MATTER FOR CONSIDERATION BY THE GENERAL ASSEMBLY Since the fiscal impact on the State, contractors, and subcontractors under the single prime construction contracting method is not conclusive due to widely differing information, the General Assembly may wish to consider establishing a pilot program to evaluate the effectiveness of various construction contracting methods that:
AGENCY RESPONSES Agency responses to this study are in Appendix L (see pages 137 147.
WILLIAM G. HOLLAND Auditor General WGH\AD April 2002 |
||||||||||||