REPORT
Management Audit ILLINOIS DEPARTMENT OF TRANSPORTATIONS ROAD CONSTRUCTION PROGRAM
Released: May 1998
State of Illinois WILLIAM G. HOLLAND
Iles Park Plaza |
SYNOPSIS Legislative Audit Commission Resolution 111 LAC Resolution Number 111 directed the Auditor General to conduct a management audit to determine whether costs paid by the Illinois Department of Transportation (IDOT) for roadbuilding materials are comparable with costs paid by other midwestern states, why there are cost differences, and whether changes in IDOTs procurement methods are warranted. Based on a review of calendar year 1996 data for Illinois and six other midwestern states (Indiana, Iowa, Kentucky, Missouri, Ohio, and Wisconsin), we found:
This audit makes 12 recommendations to help control roadbuilding costs through the procurement process. IDOT fully or partly concurred with all of the recommendations. |
In 1996, IDOT awarded 889 road construction contracts for a total contract of $896 million. |
REPORT CONCLUSIONS The Illinois Department of Transportation (IDOT) is responsible for constructing the States highway system. IDOT uses contractors for most road construction activities. In 1996, IDOT awarded 889 construction contracts for a total contract amount of $896 million. We compared IDOTs roadbuilding material costs with those of six other midwestern states: Indiana, Wisconsin, Iowa, Missouri, Kentucky, and Ohio. Comparison of unit costs between states is complex because of a variety of factors. We found considerable variations in the unit cost of selected pay items reported by IDOT and the other six states reviewed. A pay item is comprised of several types of costs, including labor, materials, equipment, and contractors overhead. In general, IDOTs pay item unit costs were higher. For example, Illinois unit cost for a ton of surface course asphalt was almost 30 percent higher than the average unit cost reported by the other states. Illinois unit cost for a square yard of portland cement concrete pavement was 17 percent higher than the other six states average. In contrast, IDOTs unit cost for structural steel was 12 percent below the average paid by the other states. There are a number of factors which contribute to these cost differences. In general, Illinois highway construction labor costs were higher than other midwestern states. Other factors, such as selected higher material costs, labor practices, quantity of the pay item purchased, and differences in project requirements, also affect Illinois pay item unit costs. States also report costs differently which accounts for some unit cost differences. For example, Illinois includes certain costs in selected pay items, such as mobilization and quality control/quality assurance, which some other states report separately. The amount of the cost differences attributable to these factors is difficult to project because of the varying nature and composition of pay items, size and type of the projects, and ways in which contractors structure their bids. There are, however, several factors related to IDOTs contracting process that may also contribute to Illinois higher costs. While the number of contracts IDOT awarded to single bidders has decreased from 18 percent in the period 1987 through 1991 to 12 percent in 1996, further improvement is warranted. For all contracts awarded in 1996, when there were multiple bidders, the award amount averaged 10.88 percent below IDOTs estimated cost for the project. When there was only one bidder, the award amount averaged 0.64 percent above IDOTs estimate. If the single bid contracts had come in at 10.88 percent below the estimate (as occurred on multiple bid contracts), the award amounts would have been $8.9 million less. IDOTs current efforts to increase competition are limited. For example, IDOT does not routinely contact companies that received bid authorization but did not bid to determine why they did not bid. Also, while IDOT has general guidelines to govern its award decisions, it has not developed formal award policies or procedures, such as when to rebid a project if all proposals exceed the States estimate. We reviewed 43 projects rebid by IDOT in 1996. When these projects were rebid, the new low bid total ($21.2 million) was 8 percent lower than the original low bid total ($23.1 million), yielding a savings of $1.9 million. In 31 of the 43 projects, the original low bidder submitted an even lower bid when the project was rebid. Other aspects of IDOTs contracting process which may limit competition include publishing the names of contractors authorized to bid and releasing project estimate amounts after the bid opening. Both practices provide contractors with information they can use to limit competitive proposals. Finally, the accuracy of IDOTs project estimates could be improved. We found wide variation in the accuracy of estimates by IDOT district. Forty-six percent of IDOTs estimates were within 10 percent of the lowest bid in 1996. Project estimates serve the critical role of controlling contract award amounts. IDOTS ROAD CONSTRUCTION PROGRAM The Illinois Department of Transportation is responsible for constructing the
States highway system. IDOT uses outside contractors for most roadbuilding
activities. Digest Exhibit 1 summarizes road construction contracts by IDOT district.
During calendar year 1996, IDOT awarded 889 road construction contracts totaling $896
million. Just over 40 percent of all the contract dollars awarded were for projects
located in IDOT District One (Cook & surrounding counties). (Report pages 3-6) |
Digest
Exhibit 1 |
||||
District |
Number |
% of Total |
% of |
Total |
1 |
201 |
22.61% | 40.29% | $361,088,343 |
2 |
128 |
14.40% | 10.25% | $91,871,619 |
3 |
92 |
10.35% | 8.81% | $78,973,269 |
4 |
78 | 8.77% | 6.60% | $59,146,039 |
5 |
68 | 7.65% | 6.19% | $55,498,488 |
6 |
93 | 10.46% | 10.16% | $91,091,115 |
7 |
74 | 8.32% | 3.90% | $34,992,823 |
8 |
103 | 11.59% | 8.89% | $79,671,829 |
9 |
47 | 5.29% | 4.62% | $41,412,250 |
Statewide |
5 | .56% | .28% | $2,543,219 |
Total |
889 | 100% | 100% | $896,288,995 |
Note: Percentage totals may
not add due to rounding Source: OAG analysis of IDOT data |
In 1996, Illinois' average unit costs were higher than other midwestern states in 9 of 10 categories compared.
Many factors contribute to differences between the unit cost of road construction pay items, such as higher labor costs in Illinois, differences in project specifications, and diffrences in cost reporting.
The amount of competition for road contracts affects construction costs. |
ROADBUILDING MATERIAL COSTS Digest Exhibit 2 shows that when comparing calendar year 1996 statewide average unit costs for the most used road construction materials, Illinois unit costs were higher than the average of the other midwestern states in 9 of 10 categories compared, including excavation, asphalt products, reinforcing steel, and concrete products. For example, Illinois unit cost for a ton of surface course asphalt was almost 30 percent higher than the average unit cost reported by the other states. Illinois unit cost for a square yard of portland cement concrete pavement was 17 percent higher than the other six states average. In contrast, IDOTs unit cost for structural steel was 12 percent below the average paid by the other states. A comparison of individual projects also found that Illinois unit costs per pay item were generally higher than the unit costs paid by other states. Unit costs for roadbuilding pay items also varied within regions of Illinois. (Report pages 13-39) REASONS FOR VARIANCES IN ROADBUILDING COSTS Many factors contribute to differences between the unit cost of road construction pay items in Illinois and other midwestern states. Unit costs are based on the average of all low bidders costs and include not only material costs but also job-specific costs such as labor and equipment. Because each road construction job is unique, the unit costs for individual projects may vary considerably. The notes to Digest Exhibit 2 address factors affecting pay item average unit costs. IDOT has limited control over some factors, such as the generally higher labor costs in Illinois (e.g., higher prevailing wage rates, labor practices, and workers compensation rates). Other cost variables include whether the project is in a predominantly urban or rural area, the amount of competition in the area, the quantity of each material used in the project, the availability and quality of materials, differences in cost reporting among states (such as whether mobilization and quality control/quality assurance costs have separate pay items or are included as part of other pay items), differences in project requirements, and varying legal requirements among states. (Report pages 41-54) COMPETITION FOR ROAD CONTRACTS The amount of competition for road contracts affects construction costs. While the number of contracts IDOT awarded to single bidders decreased from 18 percent in the period 1987 through 1991 to 12 percent in 1996, further improvement is warranted. Single bid contracts awarded in 1996 had significantly higher award amounts relative to IDOTs estimate than did multiple bid contracts. Digest Exhibit 3 shows that the award amount for IDOTs 106 single bid contracts in calendar year 1996 averaged 0.64 percent above IDOTs estimate, but the 783 multiple bid contracts were 10.88 percent below IDOTs estimate. If single bid contracts had come in at 10.88 percent below the estimate, the total amount awarded would have been reduced by approximately $8.9 million. Single bid contracts were generally concentrated in IDOT Districts 3, 5, and 7. These districts are located in eastern Illinois along the Indiana border. |
|
The differences in average unit costs by specific pay item shown in Exhibit 2-4 can be attributable to a number of factors. A pay item is comprised of several types of costs, including labor, materials, equipment, and contractors overhead. There are many factors which impact pay item costs reported by the various states. For example, Illinois generally has higher labor costs than the other states. Consequently, the higher cost of labor in Illinois can increase IDOTs pay item unit costs versus those in other states. Other factors which impact costs include:
The amount of cost differences attributable to these factors is difficult to project because of the varying nature and composition of pay items, size and type of projects, and ways in which contractors structure their bids. There were also differences in pay item reporting between Illinois and the other states reviewed. For example, Illinois does not separate mobilization costs from its pay items, which other states report separately. Consequently, the cost for some IDOT pay items may be higher because of the inclusion of mobilization costs. Other differences identified based on our review and a recent survey conducted by IDOT included: Surface Course and Binder Course Asphalt: Unit costs for Missouri and Wisconsin exclude aggregate certification costs (about $1.00 per ton in Illinois). Also, Wisconsin unit costs for surface course asphalt exclude QC/QA (estimated at $1 - $2 per ton). Conversely, Illinois unit costs do not include anti-strip costs whereas Kentucky and Missouri unit costs do (estimated by IDOT at about $0.65 per ton). Base Course Asphalt: Illinois uses base course asphalt primarily for temporary roads, side streets, or detour roads which can be a more costly use than new construction, according to IDOT. Portland Cement Concrete: Unit costs for Indiana exclude the cost of sealing contraction joints. Indiana, Iowa, Kentucky and Missouri unit costs exclude subgrade preparation. Conversely, Illinois unit cost does not include QC/QA costs whereas Kentucky unit costs do. In addition, the thickness of the portland cement pavement varied among the states, with Illinois 9 ½ inch pavement being the thinnest of the states reviewed. Structural Concrete: Unit costs for Indiana, Iowa, Missouri, and Wisconsin exclude parapet costs; Missouri also excludes sidewalk costs. Kentucky and Wisconsin unit costs exclude the cost of protective shields. Conversely, Illinois unit cost does not include admixtures whereas the Iowa unit cost does. Also, Illinois unit cost does not include QC/QA whereas Kentucky and Ohio unit costs do. Earth Excavation: Illinois unit costs for excavation include the costs of clearing, undercutting, compaction, dust control, overhaul, borrow material, settlement platforms, and disposal of unsuitable materials. Many of these items are paid for separately in other states, and may, therefore, lower their unit costs for excavation. For a more detailed discussion of the pay items reviewed and the various factors
affecting pay item unit costs, see chapters two through five of the audit report. |
Digest Exhibit 3 |
||||
Contracts Awarded |
Estimate |
Award |
Variance
|
|
Single Bids | 106 |
$ 77,194,790 |
$ 77,692,326 |
0.64% above |
Multiple Bids | 783 |
$918,558,994 |
$818,596,669 |
10.88% below |
Source: OAG analysis of IDOT data |
IDOT's current efforts to increase competition are limited.
There are several changes IDOT can make to its procurement process to help control road construction costs.
The Department fully or partly concurred with all of the recommendations. |
IDOTs current efforts to increase competition are limited. For example, IDOT does not routinely contact companies that received bid authorization but did not bid to determine why they did not bid. Also, while IDOT has general guidelines to govern its award decision, it has not developed formal award policies or procedures, such as when to rebid a project if all proposals exceed the States estimate. We reviewed 43 projects rebid by IDOT in 1996. When these projects were rebid, the new lowest bid total was 8 percent lower than the original low bid total, yielding a savings of $1.9 million. In 31 of the 43 projects, the original low bidder submitted an even lower bid when the project was rebid. We recommended that IDOT increase its efforts to encourage and develop competition on road construction projects in the State, and establish formal guidelines governing when to award roadbuilding contracts. (Report pages 55-67) OTHER PROCUREMENT ISSUES There are several other changes IDOT can make to its procurement process to help control road construction costs. These changes include improving the accuracy of cost estimates to avoid accepting inflated bids or rejecting valid ones. As shown in Digest Exhibit 4, 46 percent of the low bids on the 948 projects let by IDOT in 1996 were within 10 percent of estimate. The Federal Highway Administrations contracting guidelines state that at least 50 percent of the project cost estimates should be within 10 percent (plus or minus) of the actual low bids. We also found wide variations among IDOT Districts in the frequency that low bids were within 10 percent of the estimate. Regarding other procurement-related issues, we recommended IDOT should discontinue the practice of releasing cost estimates to the public, continue its efforts to identify and evaluate differences in project requirements between Illinois and other states to identify where cost savings can be realized, contact contractors whose prequalification lapses to determine the causes or reasons, improve controls over the letting process, take steps to avoid unnecessary change orders, and continue to explore the uses of value engineering and other innovative contracting procedures. (Report pages 69-87) RECOMMENDATIONS The audit report includes 12 recommendations to the Department of Transportation. In their written response, the Department fully or partly concurred with all of the recommendations. Excerpts of their response are included after each recommendation, and their entire response is in Appendix G of the audit report.
May 1998 |